Power restored in Toronto after crane hits transmission line
Power has been restored in Toronto's downtown core after an hours-long outage caused major disruptions in the city Thursday.
Hydro One confirmed the restoration around 8 p.m., saying that some 10,000 residents and businesses who had been without power for most of the afternoon and evening now have electricity.
“Safety is always our top priority. We know this power outage has made today exceptionally difficult for many of you, and we appreciate your patience,” David Lebeter, chief operating officer of Hydro One, said in a statement.
“We had all available resources helping to restore power as quickly and safely as possible. I want to thank all of those affected by this outage for their patience and Toronto Fire and Toronto Hydro for their collaboration.”
Officials said the outage was caused by a large crane that struck a high-voltage transmission line earlier in the day.
In a statement, officials confirmed that a barge moving a crane in the upright position ran into the lines in the Port Lands area. This in turn caused a ripple effect, resulting in damage to equipment at a power station near The Esplanade and Lower Sherbourne Street.
"In the coming days, crews will continue work on the lines damaged by the crane."
Several blocks within the Financial District and the area of Yonge and Dundas streets, including Yonge-Dundas Square itself, lost power just after 12:30 p.m.
The big screens that usually display advertisements in that area were also down.
Other areas affected by the outage included the Toronto police headquarters, St. Lawrence Market, Toronto City Hall, and the Eaton Centre, which was forced to partially close at one point but has since reopened.
Toronto Transportation Services said the outage spanned at least a four-block radius.
Toronto Hydro's outage map showed the areas within College Street to the Gardiner Expressway and between the Bayview Extension and University Avenue were without power.
- LIVE LOOK: Toronto Hydro outage map
Toronto Hydro told CP24 earlier in the day that a large crane in the city’s Port Land’s neighbourhood had struck a high-voltage transmission line, though it was unclear at that time if that was the cause of the outage.
In a follow up tweet, Hydro One -- which had been working alongside the city’s power utility throughout the outage -- all but confirmed the impact of the crane was the source of the outage with images attached of the “transmission circuit that's been affected.”
It’s unclear how the crane was able to make contact with the high-voltage line that left so much of the downtown core without electricity.
TORONTO LAUNCHES INVESTIGATION INTO OUTAGE
Officials with the City of Toronto said they have launched a full investigation into the downtown outage.
In a statement, officials said the outage may have been caused by a subcontractor to Southland-Astaldi Joint Venture (SAJV), a contractor for the Ashbridges Bay Treatment Plant outfall project.
"An investigation is currently underway after a barge with a crane came into contact with overhead Hydro One wires," the city said. "The incident occurred away from the construction sites while the barge was in transit within the Port of Toronto water ways."
The city said it has also requested a full report from SAJV in order "to understand what happened and what needs to be done to ensure this does not happen again."
CTVNews.ca Top Stories
Ontario Provincial Police arrest 64 suspects in child sexual exploitation investigation
Ontario Provincial Police say 64 suspects are facing a combined 348 charges in connection with a series of child sexual exploitation investigations that spanned the province.
AstraZeneca says it will withdraw COVID-19 vaccine globally as demand dips
AstraZeneca said on Tuesday it had initiated the worldwide withdrawal of its COVID-19 vaccine due to a 'surplus of available updated vaccines' since the pandemic.
'Summer of discontent': Federal unions vow to fight new 3-day a week office mandate
Federal unions are launching legal challenges and encouraging public sector workers to file "tens of thousands" of grievances over the new mandate requiring federal workers to return to the office at least three days a week in the fall.
Toronto police seek suspect vehicle after security guard shot outside Drake's mansion
Toronto police are seeking help from the public as they continue to investigate a shooting that seriously injured a security guard outside rapper Drake's mansion.
'Ozempic babies': Reports of surprise pregnancies raise new questions about weight loss drugs
Numerous women have shared stories of 'Ozempic babies' on social media. But the joy some experience in discovering pregnancies may come with anxiety about the unknowns.
OPINION What King Charles' schedule being too 'full' to accommodate son suggests
Prince Harry, the Duke of Sussex, has made headlines with his recent arrival in the U.K., this time to celebrate all things Invictus. But upon the prince landing in the U.K., we have already had confirmation that King Charles III won't have time to see his youngest son during his brief visit.
Seafood, eat food: Calgary Stampede releases Midway menu
The Calgary Stampede has released its menu of sweet, salty and spicy treats available on the Midway for the Greatest Outdoor Show on Earth.
Boy Scouts of America is rebranding. Here's why they've changed their name
After more than a century, Boy Scouts of America is rebranding as Scouting America, another major shakeup for an organization that once proudly resisted change.
These snakes not only fake their own deaths, they use gory special effects to do it
Awards season may be over for human actors this year, but there’s no rest for some of nature’s most audacious thespians.