Busy Toronto streetcar to shut down for 20 months starting in May
A busy streetcar in the heart of downtown Toronto could be shut down for about 20 months starting right before the summer.
As of early May, commuters hoping to jump on the 501 streetcar on Queen St. will instead have to queue up for a shuttle bus.
In a report set to be presented at next week’s Toronto Transit Commission (TTC) board meeting, officials say that utility work to allow the streetcar to divert around construction for the new Ontario Line has delayed the construction for the new tracks.
“Currently, the TTC, Metrolinx, City of Toronto and various utility owners are working very closely to resolve all of the utility conflicts and relocations as expediently as possible,” the report says.
“Metrolinx has identified that the potential delay to complete the streetcar detour work will result in approximately 20 months of shuttle bus service commencing in early May 2023.”
- Download our app to get local alerts on your device
- Get the latest local updates right to your inbox
A section of Queen Street in Toronto is anticipated to close for nearly five years for the construction of the new subway stop, located at Yonge and Queen streets, connecting to Line 1.
New tracks are being laid down along Adelaide Street, as well as nearby side streets, to allow for the streetcar to divert without using shuttle busses.
The report notes the work was “substantially completed” in late 2022, but adds the TTC is still “refining the detailed design of the infrastructure” with the city and Metrolinx, the provincial agency set to operate the Ontario Line.
Construction along the remaining areas were expected to start last year, however, officials say a utility issue were identified that “surpassed previous expectations and has delayed the start of the construction of the streetcar tracks for the diversion.”
“The TTC is still working closely with Metrolinx and the City on exploring options to optimize the construction schedule of the Adelaide civil and streetcar track construction work to reduce the duration of shuttle bus service,” the report reads.
A proposed map of the Ontario Line is pictured. (Metrolinx)
The Ontario Line is a large part of the Doug Ford government’s transit expansion plan for the Greater Toronto and Hamilton Area. All the costs are being covered by the province, which is anticipated to be more than $1 billion per kilometre—nearly double initial estimates.
Documents from Infrastructure Ontario showed two contracts totalling $15 billion have already been awarded.
The 15-stop, 15.6-kilometre extension, which will run from Exhibition Place through the downtown core along Queen Street before heading north to the Ontario Science Centre, is expected to be completed by 2031.
Businesses set to be impacted by the construction are asking for transparency and accountability following the Eglinton Crosstown LRT, which caused extensive construction along busy corridors and took much longer than anticipated.
CTVNews.ca Top Stories
'My family doctor just fired me': Ontario patients frustrated with de-rostering
Dozens of Ontarians are expressing frustration in the province’s health-care system after their family doctors either dropped them as patients or threatened to after they sought urgent care elsewhere.
Canada Post cracks down on Nunavut loophole to get free Amazon Prime shipping
Amazon's paid subscription service provides free delivery for online shopping across Canada except for remote locations, the company said in an email. While customers in Iqaluit qualify for the offer, all other communities in Nunavut are excluded.
Adopted daughter in the Netherlands reunited with sister in Montreal and mother in Colombia, 40 years later
Two daughters and a mother were reunited online 40 years later thanks to a DNA kit and a Zoom connection despite living on three separate continents and speaking different languages.
Michael Cohen: A challenging star witness in Donald Trump's hush money trial
He once said he would take a bullet for Donald Trump. Now Michael Cohen is prosecutors' biggest piece of legal ammunition in the former president's hush money trial.
Millions of Canadians have been exposed to potentially toxic chemicals, and they're not going anywhere
For decades, North Bay, Ontario's water supply has harboured chemicals associated with liver and developmental issues, cancer and complications with pregnancy. It's far from the only city with that problem.
German men with the strongest fingers compete in Bavaria's 'Fingerhakeln' wrestling championship
Despite the threat of dislocated fingers and strained muscles, over 150 Bavarian men came together Sunday to compete in Germany’s unique national championship of “Fingerhakeln,” or finger wrestling.
As Israel pushes deeper into Rafah, Hamas regroups elsewhere in ungoverned Gaza
Israeli forces were battling Palestinian militants across the Gaza Strip on Sunday, including in parts of the devastated north that the military said it had cleared months ago, where Hamas has exploited a security vacuum to regroup.
4th Indian national arrested, charged with murder of Hardeep Singh Nijjar
Homicide investigators in B.C. say murder charges have been laid against a fourth Indian national in connection to the killing of Sikh activist Hardeep Singh Nijjar outside a Surrey gurdwara last year.
Balancing act: Canadian North’s first Inuk CEO juggles Arctic airline challenges
With carriers' flight volumes above the 60th parallel hovering below pre-pandemic levels, Canadian North’s first Inuk CEO now bears the task of balancing those financial and logistical challenges with the needs of communities for which she feels a deep affinity.