'It is quite a shock:' Cost of building the Ontario Line has nearly doubled
The cost of building the Ontario Line has nearly doubled from initial estimates and could end up coming in at more than $1 billion per kilometre.
When the Ford government first unveiled plans for the 15.6-kilometre relief subway line in 2019, it pegged the cost at $10.9 billion and said that it would be completed by 2027.
However, new documents released by Infrastructure Ontario this month show that two contracts totalling $15 billion have already been awarded for the project, which is now expected to be completed in 2031.
Request for Proposals (RFPs) have also been issued for another two contracts to build the north portion of the line.
Infrastructure Ontario has previously suggested that these contracts, once awarded, will add between $1-2 billion each to the total cost.
That, in turn, could push the price tag as high as $19 billion.
“It’s quite a shock and should be a shock to people,” NDP Infrastructure Critic Jennifer French told CP24 this week. “I think that factoring in inflation is you know, a realistic thing to talk about, but to blame this entirely on that, nobody's buying that.”
One of the biggest factors driving up the cost of the Ontario Line is a contract awarded to a consortium of companies to operate and maintain the system for the next 30 years.
Metrolinx previously estimated the value of that contract at greater than $2 billion but when the contract was formally announced on Nov. 17 its value had shot up to $9 billion.
The other contract to build the southern portion of the line from Exhibition Place to west of the Don River was initially pegged at $4 billion but came in at $6 billion when it was announced earlier this month.
In a statement provided to CP24, a spokesperson for the Ministry of Transportation said that “construction projects worldwide are facing economic challenges with rising inflation costs and supply chain shortages,” a phenomenon which is “not unique to the Ontario Line.”
French, however, told CP24 that the Ford government owes taxpayers a more fulsome explanation.
She also expressed concern that the latest documents released by Infrastructure Ontario move the estimated execution date for the final project agreement back two years to 2026.
At this point, it is unclear how that might impact the timeline for the construction of the 15-stop subway line.
CP24 did ask the ministry whether the completion date will be further delayed but was not provided a response.
“I guess we'll have to leave it to each individual best guess when it will actually be delivered because we don't have the behind the scenes information that we would need (to make that determination),” French said. “You know, this is a major construction project. This is a massive infrastructure plan that we don't really have any details about and then when we get to see real numbers here, like in this update, I think we all have a reason to be very nervous that this is going to cost a lot of money and a lot of time.”
Ontario Line is part of $28.5 billion plan
The Ford government chose to make the Ontario Line the centrepiece of a $28.5 billion transit expansion plan for the Greater Toronto and Hamilton Area announced in 2019, effectively replacing another planned relief subway line project that was being pursued by the City of Toronto.
In a statement, Ministry of Transportation spokesperson Dakota Brasier said the project, once complete, will “see almost 400,000 passengers every day, reduce crowding on existing subway lines and put 57,000 jobs within a 45 minute transit commute to Toronto.”
She said that it will also “generate more than $10 billion in economic benefits.”
But concerns are nonetheless being raised about the rising price tag.
Toronto’s plans for a relief subway line previously called for a smaller eight-station subway that would have ended at Pape Station.
Planning work was well underway on that line when the Ontario Line was announced in 2019.
“Ontario needs investments in public transportation, but we also need transparency and responsible oversight from our government on these projects,” Liberal Infrastructure Critic Stephanie Bowman said in a statement. “The Conservatives must come clean and tell Ontarians why the government’s hallmark transportation project is running far over budget and well past its initial completion date.”
CTVNews.ca Top Stories
Donald Trump picks former U.S. congressman Pete Hoekstra as ambassador to Canada
U.S. president-elect Donald Trump has nominated former diplomat and U.S. congressman Pete Hoekstra to be the American ambassador to Canada.
'Ding-dong-ditch' prank leads to kidnapping, assault charges for Que. couple
A Saint-Sauveur couple was back in court on Wednesday, accused of attacking a teenager over a prank.
Border agency detained dozens of 'forced labour' cargo shipments. Now it's being sued
Canada's border agency says it has detained about 50 shipments of cargo over suspicions they were products of forced labour under rules introduced in 2020 — but only one was eventually determined to be in breach of the ban.
BREAKING ICC issues arrest warrants for Israel's Netanyahu, Gallant and Hamas leader
The International Criminal Court in The Hague said on Thursday that it had issued warrants for the arrest of Hamas leader Mohammed Diab Ibrahim Al-Masri (also known as Mohammed Deif) and Israel's Prime Minister Benjamin Netanyahu and its former defence minister Yoav Gallant.
Genetic evidence backs up COVID-19 origin theory that pandemic started in seafood market
A group of researchers say they have more evidence to suggest the COVID-19 pandemic started in a Chinese seafood market where it spread from infected animals to humans. The evidence is laid out in a recent study published in Cell, a scientific journal, nearly five years after the first known COVID-19 outbreak.
REVIEW 'Gladiator II' review: Come see a man fight a monkey; stay for Denzel's devious villain
CTV film critic Richard Crouse says the follow-up to Best Picture Oscar winner 'Gladiator' is long on spectacle, but short on soul.
Alabama to use nitrogen gas to execute man for 1994 slaying of hitchhiker
An Alabama prisoner convicted of the 1994 murder of a female hitchhiker is slated Thursday to become the third person executed by nitrogen gas.
This is how much money you need to make to buy a house in Canada's largest cities
The average salary needed to buy a home keeps inching down in cities across Canada, according to the latest data.
Police report reveals assault allegations against Hegseth
A woman told police that she was sexually assaulted in 2017 by Pete Hegseth after he took her phone, blocked the door to a California hotel room and refused to let her leave, according to a detailed investigative report made public late Wednesday.